Rhode Island Affordable Development Activities 

Reynolds Farm Senior Housing II

North Kingstown

Developer: Valley Affordable Housing Corp.

  • Anticipated Completion Date: Q4 2026
  • Total Units: 40
  • Total Affordable Units: 40
  • Affordability: 30% – 60% AMI
  • Construction Status: 41% complete

 Funding Sources and Amount:

Source Amount
4% LIHTC $5,575,552
Deferred Development Fee $250,000
General Partner Capital $100
HOME $1,000,000
Housing Trust Fund $1,340,000
DAH* $7,860,000
RIH First Mortgage $625,000

Total Development Cost: $16,650,652

RIHousing-administered SFRF Funds Expended:  $2,754,549

*Sources funded by the State Fiscal Recovery Funds (“SFRF”).

 

 

 

Affordable housing under construction

Site visit: 2025.4.22